In December 2021 work started on the pipework for the plumbing. With the help of a friend, plastic piping was used initially, but it was a nightmare uncoiling it, so Rod opted for brass pipes as was his original intention. The ducts for the extractors in the bathrooms, and toilets were installed as well.
In March 2022 the last of the stunned glass windows were completed and reinstalled in the dining room area. A milestone after starting the project in October 2019, involving 40 windows, some of which were very badly damaged and needed a lot of work to restore them. The final three windows were the biggest, requiring great care in lifting them into place and fixing them into the brackets.