Bedrooms, Master Bedroom, and a forest of timbers

Arnsheen




The slate floor was laid over the screed, in just the nave for now. The first phase had a protection cover of sheeting and then the framing for the 2 downstairs bedrooms, en-suites, walk in wardrobes, airing cupboard and downstairs toilet was erected.






The video above shows the two bedrooms downstairs with the ensuites.....


Once the downstairs framing was complete, the master bedroom upstairs could be started. This would be the first time that we could get up the tower spiral staircase and walk into the room, walk-in wardrobe and ensuite.


The framing of the Master Bedroom floor






The underfloor now fully put down. This is facing towards the transept where ensuite and walk in wardrobe will go


Facing towards the big rose window at the other end of the room, with door into tower





Once the underfloor had been laid down, framing could be done on the wall where the rose window is, there ensuite bathroom and walk-in wardrobe. The stairs and landing down to the transept could also be started.













The framing was then fixed to the side walls and rose window. We estimate approximately 1mile of timber lengths were used in the framing for the bedrooms, en-suite s and walk in wardrobes 😱😱